SUBSCRIBE NEWS LETTER

APTEL

4-Year Project Delay Proves Expensive For Rajasthan Solar Developer

The Appellate Tribunal For Electricity (APTEL) bench has gone with the views of the Rajasthan Electricity Regulatory Commission (RERC) in a case (appeal no 172 of 2019) involving a solar power developer, Arjun Green Power Pvt Limited against the order of the former. Case Overview: Arjun Green Power Pvt. Ltd., a solar power developer, appealed […]

Read more

A Delay Foretold. How MSEDCL Delayed a 500 MW RE Project Involving Tata Power

In looking at the orders of regulators at the state and national level (CERC and APTEL), one is regularly surprised at how common sense is regularly abandoned in favour of abundant precaution. Among state entities like discoms, the fear of being seen as biased trumps everything when it comes to a project. Be it the […]

Read more

GERC Imposes Additional Surcharge Of Rs 1/Kwh For Open Access Consumers

The Gujarat Electricity Regulatory Commission (GERC) in its latest notification proposed imposing an additional surcharge for open access consumers in the state. The state electricity regulatory body proposed imposing an additional surcharge at the rate of Re 1 per Kwh. The GERC order said that the additional surcharge for these consumers would be applicable between […]

Read more

CERC Asks Karnataka SLDC To Compensate RE Generator For Curtailment

The Central Electricity Regulatory Commission (CERC), in its latest judgement asked the Karnataka State Load Despatch Centre (SLDC) and other respondents in the case to compensate two solar power generators for curtailment. The order came to the fore when the generators moved to the central commission seeking compensation against the curtailment of renewable power due to orders […]

Read more

CERC Denies Granting ‘Change Of Law’ Benefits To Adani Green

The Central Electricity Regulatory Commission (CERC), in its latest judgment, declined to give relief to Adani Green on ‘Change of Law’ events on procedural issues. It came after Adani Green, who was a respondent in a petition filed by the Solar Energy Corporation of India (SECI). The Petition was related to the adoption of tariffs.  The Petition […]

Read more

What Is Delaying Commissioning of India’s 96 GW Under-Construction RE Projects?

A quarterly report by the Central Electricity Authority (CEA) for the period ending July 31 claims that renewable energy projects of up to 96 Gigawatt (GW) are under construction in the country. These projects are related to the renewable energy projects tendered through the Solar Energy Corporation of India (SECI) and other central public sector […]

Read more

Adani Green Wins Battle At TNERC With Tangedco On Tariff Applicability

In an order dated July 20, the Tamil Nadu Electricity Regulatory Commission (TNERC) has ruled in favour of Kamuthi Renewable Energy Ltd., a subsidiary of Adani Green Energy Limited  in a case involving a dispute with TANGEDCO on the applicable tariff for a 75 MW project at Kamuthi.  Tangedco, in an order September 2016, had […]

Read more

Transmission Firm Gets No Relief From CERC For Projects In Himalayan Region

The Central Electricity Regulatory Commission (CERC), in its latest order, denied any relief to a transmission network service provider over a plea to revise its Operations and Maintenance (O&M) norms. The petitioner-Teestavalley Power Transmission Limited (TPTL), in its plea before the CERC, asked the Commission to relax the norms under its “power to relax” powers.  TPTL […]

Read more

RERC Declines To Allow Lower Tariffs for Private Hospitals In Rajasthan

  In its latest order, the Rajasthan Electricity Regulatory Commission (RERC) declined to give any relief to the Indian Medical Association (IMA). The Rajasthan IMA branch had filed a review petition before the RERC to review its earlier order passed on March 31, 2023. The earlier order had also rejected the demand of a special tariff […]

Read more
      SUBSCRIBE NEWS LETTER
Scroll