CERC Brings Relief on Safeguard Duty for ACME Solar and Arisun

CERC Brings Relief on Safeguard Duty for ACME Solar and Arisun

CERC has provided compensatory relief for ACME and Arisun after accepting their plea to consider the imposition of the safeguard duty as “Change in Law”.

CERC ACME Arisun

The Central Electricity Regulatory Commission (CERC) has in its latest order, provided compensatory relief for ACME Jaipur Solar and Arisun Clean Energy after accepting their plea to consider the imposition of the safeguard duty as “Change in Law”.

ACME Jaipur Solar, a wholly-owned subsidiary of ACME Solar and Arisun Clean Energy, a special purpose vehicle formed by Sprng Energy, had filed in separate petitions with the commission, seeking the imposition of safeguard duty on the import of solar modules as Change in Law in terms of the PPA which had led to an increase in the additional capital expenditure for the projects.

And, to direct the respondents in the case to form a suitable payment mechanism to compensate the petitioners for the increase in the expenditure incurred by the developers.

The respondents, in this case, were M.P. Power Management Company Limited (MPPMCL), Delhi Metro Rail Corporation (DMRC), and Rewa Ultra Mega Solar Limited (RUMSL).

Arinsun during the hearing further stated that the total cost of modules after the imposition of safeguard duty was about Rs 610 crore compared to Rs 487 crore before the imposition of the safeguard duty. That involved with the taxes involved, the firm stated that the increase is more than Rs 32 crore on the landed cost of the solar PV modules on account of the imposition of the safeguard duty.

The Commission in its order stated that it has already held that the imposition of the ‘safeguard duty’ as an event covered under ‘Change in law’ and that the actual amount of the ‘safeguard duty’ imposed by the competent authority and paid by the petitioners must be compensated.

Hence, the commission has directed the petitioners to make available all the relevant documents exhibiting clear, and one to one correlation between the projects and the supply of imported goods until the commissioning certificate is issued following the provisions of the PPA, supported by relevant invoices and auditor’s certificate. The respondents are to reconcile the claims after receiving the relevant documents and compensate for the amount claimed.

The compensation should be paid within 60 days from the date of the order or from the date of submission of claims by the petitioners whichever is later, failing which it shall attract late payment surcharge.

For more information click here.

"Want to be featured here or have news to share? Write to info[at]saurenergy.com

Ayush Verma

Ayush is a staff writer at saurenergy.com and writes on renewable energy with a special focus on solar and wind. Prior to this, as an engineering graduate trying to find his niche in the energy journalism segment, he worked as a correspondent for iamrenew.com.