MERC Orders SECI to Compensate MSEDCL for Delayed Solar Projects By Ayush Verma/ Updated On Thu, Feb 18th, 2021 MERC has directed SECI to compensate MSEDCL as per a Power Sale Agreement (PSA) signed between the two entities for delayed solar projects. The Maharashtra Electricity Regulatory Commission (MERC) in its latest order has directed the Solar Energy Corporation of India (SECI) to compensate Maharashtra State Electricity Distribution Company Limited (MSEDCL) as per a Power Sale Agreement (PSA) signed between the two entities for procurement of solar power. MSEDCL had filed a petition with the commission seeking compensation from SECI (the Intermediary Procurer) as per the PSA and the compensation on account of delay in achieving the Scheduled Commercial Operation Date (SCoD) as per Power Purchase Agreement (PPA) executed between SECI and Solar Power Developers (SPD). MSEDCL’s main request to the commission were: Hold and declare that SECI has been unable to perform its timely commitments under the PSA’s for delivery of the agreed quantum of power, Direct SECI to compensate MSEDCL to the tune of Rs 131.72 crore. as losses on account of short-supply by SECI thereby forcing MSEDCL to fulfill its RPO targets through other mechanism/sources, Direct SECI to reimburse the payment of Rs 13.74 crore towards the amount for reduction of tariff from CoD to March 31, 2019, for the solar projects, Direct SECI to raise future invoices with respect to Batch-III and Batch-IV projects at the revised tariff rates. Earlier SECI had objected to the jurisdiction of this Commission to entertain the Petition. After hearing both the parties, the Commission had ruled that it did in fact hold jurisdiction in the matter. New RE Policy in Maharashtra to Attract Rs 75,000 Cr Investments: Raut Also Read Back Story: MSEDCL Petition to Float Open Tenders Under MSKVY Partly Approved by MERC Also Read The Ministry of New and Renewable Energy (MNRE) had announced Jawaharlal Nehru National Solar Mission (JNNSM) in 2009. Under Phase-II, Batch-III of JNNSM, MNRE had announced a scheme for “setting up of 2000 MW grid-connected solar PV power projects – state specific VGF (Viability Gap Funding) scheme” which was proposed to be implemented by SECI. The power procured under the said scheme could be utilised for fulfilment of solar RPO target. MSEDCL had given consent to MNRE to participate in the proposed JNNSM for procurement of solar power from SECI which was available at a cheaper rate. SECI had carried out two separate competitive bidding for selection of SPDs for 500 MW projects in each case to be set up in Maharashtra for sale to MSEDCL based on the RfS dated August 27, 2015, and dated February 24, 2016. This makes total capacity of projects to 1000 MW, for which SECI and MSEDCL entered into two PSA’s on November 4, 2016, and December 1, 2016, wherein SECI undertook to sell ‘Solar Power to MSEDCL as per the terms of the PSA by buying the same from the selected SPDs on a back-to-back basis. The scheduled commissioning dates for Batch-III projects were May 10, 2017, for open content category (450 MW) and August 16, 2017, for Domestic Content category requirement (DCR) (50 MW) category projects, respectively. Also, the scheduled commissioning dates for 500 MW Batch-IV projects was December 23, 2017. Following this, SECI started supplying power to MSEDCL from June 2017 in a phased manner. However, the commissioning of some of the projects which SECI had tied up for the sale of power to MSEDCL got delayed which led to a shortfall in supply of power as agreed under the PSA executed between MSEDCL and SECI. Further as per terms of the Power Purchase Agreement (PPA) (between SECI and SPD), there are penalty provisions for the delay in commissioning of projects such as encashment of PBG, reduction in tariff, etc. SECI has failed to fulfill its material obligations, which resulted in an additional shortfall for meeting the solar RPO target by MSEDCL and compelled MSEDCL to procure RECs. After hearing from both parties, the commission partly allowed the petition filed by MSEDCL. And has directed SECI to pass on the following benefits to MSEDCL: Compensation for the short supply of energy during Contract Year post COD of the project. Amount towards encashment of bank guarantee for the delay in commissioning of the project if such bank guarantee has been encashed post creation of fund for payment security mechanism equivalent to three months payments to the projects commissioned under the applicable MNRE guidelines. Amount of benefit accrued due to reduction in tariff of the project due to delay in commissioning of the project and henceforth raise the bill at such reduced tariff rate. Further, SECI should share the above stated details to MSEDCL and pass on any accrued benefit as directed above within a month from the date of this Order. For more information click here. Tags: Compensate, India, MERC, MSEDCL, PSA, SECI, SECI to Compensate MSEDCL, Solar Power